Tuesday, August 26, 2008

FibreC BOARDS ARRIVE


As planned, the new glass fibre concrete boards arrived this Monday at Storefront and no time was lost to begin the installation. The first board was cautiously placed and nailed. As it was before, zinc nails were used to attach the board. These now-silver-nails will eventually rust out and look just like it did before.




Architect and Board member Belmont Freeman couldn't wait to check out the new boards!






The Fascia and Soffit are also almost finished. As it is now being coated with plaster, it will soon be brilliant white and ready for the light railing system to be hung up again.


But it's not only the facade that's being restored, the restroom also gets a makeover.

Friday, August 15, 2008

LITTLE BIT OF EVERYTHING






There's a little bit of everything going on today.. The masonite board is being cut and hung over the insulation on the exterior panels. The cornice is almost finished. The interior of the gallery is right about there.. all the plaster is on and dry with some painting left to be done.


However, there seems to be some more mysterious leaks happening downstairs. The wonderful plug that was made earlier this week only worked for one hole.. now more are opening in smaller places. Let's hope August discontinues its rainy season soon..

Thursday, August 14, 2008

WATERLESS FOUNTAINS

REstrooms are next. With this, the RElocation of our sink, fridge and everything else we used to hide in there. We are now WATERLESS!

Couldn't help but wish we had one of Mr. Mutt's (a.k.a. M. Duchamp) fountains.




Then again, we managed and came up with this:

Wishful thinking!

Wednesday, August 13, 2008

COOL TOOLS






He also carries a paper dispenser hanging from his belt and whisks the plaster with a massive egg beater.

Monday, August 11, 2008

FLASH FLOOD






This morning, the thunderstorms in the city brought along an unpleasant surprise for us down in the basement.. Water finds its way into some amazing places, like the air ducts behind the walls. Thankfully, the amazing guys at Ibex Construction patched the leak with some insulation material, and all is dry here now!

Slow blogging day at Storefront you may ask? Never. Basement floods are equally as important as historic gallery restoration projects..

Friday, August 8, 2008

ALL CLOSED UP




The plywood on the interior and the insulation inside the panels are pretty much finished being installed. The unique arcade effect was nice while it lasted, and a interesting treat to all who got the chance to walk through the walls. Next up: surfacing and finishing the interior panels, and anxiously waiting the arrival of the fiberC boards!

Tuesday, August 5, 2008

IN-BETWEEN INSIDE AND OUTSIDE






Monday night we offered a sneak peek of the restoration during the opening of our barricade installation "Learning from Hangzhou" by Mathieu Borysevicz. This opening offered the unique opportunity to mingle in-between inside and outside while taking in the new barricade installation and exploring the half dressed facade structure.